Posted on: June 7, 2018

CIP Monthly Status Report – April 2018

Cogeneration Building at the Regional Wastewater Facility
In April, the New Headworks and Headworks Improvements projects advanced through Stage Gate 4: Authorization to Award Design-Build Contract. The condition assessment of 18 existing RWF buildings’ heating, ventilation, and air conditioning (HVAC) was completed for the HVAC Improvements Project. Five construction contractors were notified of prequalification to bid on the Blower Improvements Project. The Cogeneration Facility Project design-builder reached the 90 percent design milestone. The Digester and Thickener Facilities Upgrade Project contractor completed work for the 100 million gallons per day temporary pumping and pipeline system. The EPA-approved Phase 2 plan to remove PCB caulking, grout, shotcrete and concrete from the digester area began.

The County recorded the City’s Notice of Completion and Acceptance (NOCA) for the Emergency Diesel Generators Project.

Staff presented the CIP Semiannual Status Report to the Transportation and Environment Committee, and made two recommendations to the Treatment Plant Advisory Committee and City of San José City Council: award a Master Consultant Agreement for Owner’s Advisor services for the Yard Piping and Road Improvements Project; and accept the CIP Semiannual Status Report. Both recommendations were approved.

CIP Monthly Status Report – April 2018
View All CIP Monthly Status Reports
Facebook Twitter Google Plus Email